29 metre clear span steel portal frame x 200 metres long. |
|
3 x 35 tonnes capacity gantry cranes. |
|
Reinforced concrete access and inspection pits up to 150 metres in
length. |
|
Pile foundations to support main stanchions and ground
improvement by dynamic compaction to ensure minimal movement in heavily
loaded ground slab. |
|
Controlled design programme to meet environmental
requirements for continuity of drainage through provision of bypass
interceptor and new river outfalls. |
|
Advanced in-house and proprietary software applied to the
structural design process including ground modelling techniques on
difficult terrain |
|
Electronic information sharing across the project team. |